The devastation caused by floods in the town of Carlisle made the news throughout the country and prompted the Environment Agency to take immediate action to protect the local community.

VolkerGround Engineering completed the installation of numerous flood defences / cut off walls throughout the area.

The piles were driven down to rock level using our ABI TM14/17 leader rig, in some areas the pile walls were in very close proximity to residential buildings and due to the resonance free facility on our plant no damage was caused to these buildings.

Facts and figures

  • Contract value:
    £1,110,000
  • Contract duration:
    12 weeks
  • Project categories
    Sheet Piling

Learn more about this project?