VolkerGround Engineering at Hildenborough
The VolkerGround Engineering team recently mobilised to Hildenborough to support flood defence works for our client. Using our 23T zero tail swing excavator we installed AZ12-770 8.35m length piles and GU13N sheets of various lengths to form a cofferdam.
Due to the site’s restricted access and limited working room – only accessible via service and brook crossings – our compact 23T excavator was the ideal solution. The excavator allowed us to safely and efficiently complete the piling works in line with the clients specifications.